Construction and Traffic

Week of September 7

  • Concrete being poured for foundation.
  • Traffic to continue in area with regular street cleaning.

Week of September 3

  • Excavation continues.
  • Forms for concrete going in.
  • Traffic to continue in area, with regular street cleaning.

Week of August 13

  • Excavation is underway.
  • Work on foundation slated to start in September.

Week of July 30

  • Demolition nearing completion.
  • Excavation slated to begin by mid-week.
  • Tree removal completed.

Week of July 23

  • Demo is continuing until the end of July, in final clean up stage.
  • Excavation, utility and foundation work is┬áslated to begin in August.

Week of July 16

  • Demo is continuing until the end of the month.
  • Excavation, utility and foundation work is┬áslated to begin in August.

Hayward Field design updates will help access, fan experience

The University of Oregon has released updates to the reconstruction of Hayward Field that include minor changes to the overall design.


Hayward Field construction slated to start June 19

Preparations for the reconstruction of Hayward Field will be ramping up in the coming days, with crews fencing off the site starting the week of June 19.

A small team will begin the inventory process, site preparation and some preliminary salvage work this week, but activity that will affect parking as well as pedestrian and vehicle traffic in the area will commence next week.

Map and Diagram [PDF]